Key Bridge Rebuild Dashboard

Real progress. Real time.
Data as of October 1, 2026

PROJECT AT A GLANCE

230 ft

Minimum vertical clearance from the river to the bridge girders for large vessels within the navigation channel

2+ miles

Total bridge length

600+ ft

Height of the two pylons

1,600+ ft

Distance between main span pylons

3,300+ ft

Total length of cable-stayed main span

CONTRUCTION PROGRESS

Permanent Piles
South Pylon (Pier 24)

Permanent Piles Completed

55%
Complete
Permanent Piles
North Pylon (Pier 25)

Permanent Piles Completed

26%
Complete
Work Platform
South Main Line Trestle

Trestle Construction Progress

99%
Complete
Work Platform
North Main Line Trestle

Trestle Construction Progress

99%
Complete
What are permanent piles?

The piles for the north and south pylons are hollow steel pipes – over 200 feet long and 8 feet in diameter driven deep into the riverbed to support the bridge foundation and pier protection fender.

Completion of permanent piles installation for the South Pylon (Pier 24) anticipated Spring 2027.

View Permanent Pile photos HERE.

What are permanent piles?

The piles for the north and south pylons are hollow steel pipes – over 200 feet long and 8 feet in diameter driven deep into the riverbed to support the bridge foundation and pier protection fender.

Completion of permanent piles installation for the North Pylon (Pier 25) anticipated Spring 2027.

View Permanent Pile photos HERE.

Image of aerial view of South Mainline Trestle
What is a Work Platform?

A temporary structure made of 36″ steel pipe piles, steel girders, and a timber mat surface that provides direct access from land to the bridge piers for construction crews, materials and cranes. Once construction is complete, the work platforms will be removed and reused/recycled.

Completion of South Main Line Trestle (Work Platform) anticipated Fall 2026.

View Work Platform photos HERE.

Image of aerial view of North Mainline Trestle
What is a Work Platform?

A temporary structure made of 36″ steel pipe piles, steel girders, and a timber mat surface that provides direct access from land to the bridge piers for construction crews, materials and cranes. Once construction is complete, the work platforms will be removed and reused/recycled.

Completion of North Main Line Trestle (Work Platform) anticipated Fall 2026.

View Work Platform photos HERE.

COMPLETED ACTIVITIES

National Environmental Policy Act (NEPA)
Approved July 2024
100%
Complete
Pre-Construction Activities

Completed July 2025

100%
Complete
Mechanical Land Demolition

Completed February 2026

100%
Complete
Test Pile Program

Completed February 2026

100%
Complete
National Environmental Policy Act (NEPA)

The Federal Highway Administration (FHWA) approved the Categorical Exclusion (CE) for the Key Bridge Rebuild Project in July 2024. The CE confirms that the project will restore a critical interstate transportation link while avoiding significant impacts to nearby communities and natural or cultural resources. The project is expected to have substantial transportation and socioeconomic benefits and WILL NOT:

  • Significantly affect planned growth or land use in the area;
  • Require relocation of residences or businesses;
  • Change travel patterns compared with pre-collapse conditions; or
  • Impact historic, park, or recreational resources.
Pre-Construction Activities

Pre-construction activities were completed in July 2025. Activities included wind tunnel testing, survey & mapping, scour testing, property inspections, bridge alignment and geotechnical investigations.

View Pre-Construction Activities photos HERE.

Mechanical Land Demolition

Demolition of the existing bridges over land was completed in February 2026. On land, the team removed 20,000 tons of concrete decking and concrete columns, along with 160 steel girders on both the north and south sides of the bridge.

View Mechanical Land Demolition photos HERE.

Test Pile Program

The Test Pile Program was successfully completed in February 2026, confirming the strength and performance of the project’s foundation design and allowing the team to move directly into driving permanent piles. The test piles were 8 feet in diameter and over 200 feet long.

View Test Pile Program photos HERE.

PROCUREMENT MILESTONES

Overhead map of Key b/ridge Rebuild project site
South Land Approach
Advertise for Bids
Fall 2026 – Winter 2027
Construction Notice To Proceed
Late Spring 2027
Demolition & Miscellaneous Marine Work
Advertise for Bids
Completed August 25, 2026
Construction Notice To Proceed
Fall 2026
Main Span & Marine Approaches
Advertised for Request for Qualified Proposers
Completed July 21, 2026
Shortlist Identification
Fall 2026
Contract Notice To Proceed
Summer 2027
North Land Approach
Advertise for Bids
Winter 2027
Construction Notice To Proceed
Summer 2027

DESIGN MILESTONES

15% Design
  • Main Span Bridge & Marine Approaches
  • South Land Approach
  • North Land Approach
50% Design
  • Main Span Bridge & Marine Approaches
  • South Land Approach
  • North Land Approach
70% Design
  • Main Span Bridge & Marine Approaches
  • South Land Approach
  • North Land Approach
95% Design
  • South Land Approach
  • North Land Approach
100% Design
  • South Land Approach
  • North Land Approach
100% Design
  • Main Span Bridge & Marine Approaches
January
2025
August
2025
December
2025
June
2026
Anticipated
December 2026
Anticipated
Summer 2027

RECENT ACCOMPLISHMENTS

Near completion of the North Main Line Trestle (Work Platform).

Near completion of the South Main Line Trestle (Work Platform).

Advertised for the Main Span & Marine Approaches Request for Qualified proposers.

Advertised for the Demolition & Miscellaneous Marine Work bids.

WHAT'S NEXT

Continue driving permanent foundation piles and pier protection piles at the South Pylon (Pier 24).

Continue driving permanent foundation piles and pier protection piles at the North Pylon (Pier 25).

Bid opening for the Demolition and Miscellaneous Marine Work contract.

STAKEHOLDER ENGAGEMENT

145
Pop-up Events
83
Speaking Engagements
3
Industry Forums
37 K
Followers on Facebook