Key Bridge Rebuild Dashboard

Real progress. Real time.
Data as of November 1, 2026

PROJECT AT A GLANCE

230 ft

Minimum vertical clearance from the river to the bridge girders for large vessels within the navigation channel

2+ miles

Total bridge length

600+ ft

Height of the two pylons

1,600+ ft

Distance between main span pylons

3,300+ ft

Total length of cable-stayed main span

CONSTRUCTION PROGRESS

Decorative image
Foundation Piles
North Pylon (Pier 25)

Foundation Piles Completed

60%
Complete
Rendering of new bridge's Pier 25 with foundation piles highlighted under water.
What are foundation piles?

The foundation piles for the north and south pylons are hollow steel pipes – over 200 feet long and 8 feet in diameter driven deep into the riverbed to support the bridge foundation.

Completion of foundation piles installation for the North Pylon (Pier 25) anticipated Winter 2027.

View Permanent Pile photos HERE.

Decorative image
Pier Protection Piles
North Pylon (Pier 25)

Pier Protection Piles Completed

23%
Complete
Rendering of new bridge's Pier 25 with pier protection piles highlighted under water.
What are pier protection piles?

The pier protection piles for the north and south pylons are hollow steel pipes – over 200 feet long and 8 feet in diameter driven deep into the riverbed to support the pier protection fender.

Completion of pier protection piles installation for the North Pylon (Pier 25) anticipated Winter 2027.

View Permanent Pile photos HERE.

Decorative image
Foundation Piles
South Pylon (Pier 24)

Foundation Piles Completed

97%
Complete
Rendering of new bridge's Pier 24 with foundation piles highlighted under water.
What are foundation piles?

The foundation piles for the north and south pylons are hollow steel pipes – over 200 feet long and 8 feet in diameter driven deep into the riverbed to support the bridge foundation.

Completion of foundation piles installation for the South Pylon (Pier 24) anticipated Winter 2027.

View Permanent Pile photos HERE.

Decorative image
Pier Protection Piles
South Pylon (Pier 24)

Pier Protection Piles Completed

51%
Complete
Rendering of new bridge's Pier 24 with pier protection piles highlighted under water.
What are pier protection piles?

The pier protection piles for the north and south pylons are hollow steel pipes – over 200 feet long and 8 feet in diameter driven deep into the riverbed to support the pier protection fender.

Completion of pier protection piles installation for the South Pylon (Pier 24) anticipated Winter 2027.

View Permanent Pile photos HERE.

COMPLETED ACTIVITIES

Image of aerial view of North Mainline Trestle
Trestle (Work Platform)

Construction of the North Main Line Trestle (Work Platform) was completed in October 2026. The Work Platform is temporary structure made of 36″ steel pipe piles, steel girders, and a timber mat surface that provides direct access from land to the bridge piers for construction crews, materials and cranes. Once construction is complete, the work platforms will be removed and reused/recycled.

View Work Platform photos HERE.

Image of aerial view of South Mainline Trestle
Trestle (Work Platform)

Construction of the South Main Line Trestle (Work Platform) was completed in October 2026. The Work Platform is temporary structure made of 36″ steel pipe piles, steel girders, and a timber mat surface that provides direct access from land to the bridge piers for construction crews, materials and cranes. Once construction is complete, the work platforms will be removed and reused/recycled.

View Work Platform photos HERE.

Test Pile Program

The Test Pile Program was successfully completed in February 2026, confirming the strength and performance of the project’s foundation design and allowing the team to move directly into driving permanent piles. The test piles were 8 feet in diameter and over 200 feet long.

View Test Pile Program photos HERE.

Mechanical Land Demolition

Demolition of the existing bridges over land was completed in February 2026. On land, the team removed 20,000 tons of concrete decking and concrete columns, along with 160 steel girders on both the north and south sides of the bridge.

View Mechanical Land Demolition photos HERE.

Pre-Construction Activities

Pre-construction activities were completed in July 2025. Activities included wind tunnel testing, survey & mapping, scour testing, property inspections, bridge alignment and geotechnical investigations.

View Pre-Construction Activities photos HERE.

National Environmental Policy Act (NEPA)

The Federal Highway Administration (FHWA) approved the Categorical Exclusion (CE) for the Key Bridge Rebuild Project in July 2024. The CE confirms that the project will restore a critical interstate transportation link while avoiding significant impacts to nearby communities and natural or cultural resources. The project is expected to have substantial transportation and socioeconomic benefits and WILL NOT:

  • Significantly affect planned growth or land use in the area;
  • Require relocation of residences or businesses;
  • Change travel patterns compared with pre-collapse conditions; or
  • Impact historic, park, or recreational resources.

PROCUREMENT MILESTONES

Overhead map of Key b/ridge Rebuild project site
South Land Approach
Advertise for Bids
Fall 2026 – Winter 2027
Construction Notice To Proceed
Spring 2027
Demolition & Miscellaneous Marine Work
Advertise for Bids
Completed August 25, 2026
Construction Notice To Proceed
Fall 2026
Decorative image
Main Span & Marine Approaches
Advertised for Request for Qualified Proposers
Completed July 21, 2026
Contract Notice To Proceed
Summer 2027
North Land Approach
Advertise for Bids
Winter 2027
Construction Notice To Proceed
Late Spring 2027

DESIGN MILESTONES

15% Design
  • Main Span Bridge & Marine Approaches
  • South Land Approach
  • North Land Approach
50% Design
  • Main Span Bridge & Marine Approaches
  • South Land Approach
  • North Land Approach
70% Design
  • Main Span Bridge & Marine Approaches
  • South Land Approach
  • North Land Approach
95% Design
  • South Land Approach
  • North Land Approach
100% Design
  • South Land Approach
  • North Land Approach
100% Design
  • Main Span Bridge & Marine Approaches
January
2025
August
2025
December
2025
June
2026
Anticipated
December 2026
Anticipated
Summer 2027

RECENT ACCOMPLISHMENTS

Completion of the North Main Line Trestle (Work Platform).

Completion of the South Main Line Trestle (Work Platform).

Advertised for the Main Span & Marine Approaches Request for Qualified proposers.

Bids opened for the Demolition & Miscellaneous Marine Work bids.

WHAT'S NEXT

Continue driving permanent foundation piles and pier protection piles at the South Pylon (Pier 24).

Continue driving permanent foundation piles and pier protection piles at the North Pylon (Pier 25).

Award for the Demolition and Miscellaneous Marine Work contract.

STAKEHOLDER ENGAGEMENT

145
Pop-up Events
83
Speaking Engagements
3
Industry Forums
37 K
Followers on Facebook